Answer:
Step-by-step explanation:
L(d) = 189 - 7d
L(17) = 189 - 7·17 = 70 miles
After 17 days, 70 miles of track remain.
:::::
189 miles × (1 day)/(7 miles) = 27 days
It takes a total of 27 days to lay the track.