A factory has 112 workers. They have decided to change from an 8-hour working day into a 7-hour working day. How many more employees does the
company need to hire in order to keep the factory running as before?

Respuesta :

The factory need 16 more employees to hire in order to keep the factory running as before.

Time and work:

Given that A factory has 112 workers.

When worker decided to change from an 8-hour working day into a 7-hour working day.

In that case also work is same.

              [tex]112*8=m*7\\\\m=\frac{112*8}{7} =128[/tex]

Where m is number of worker require after changing working hours.

Number of more employees = 128 - 112 = 16

Hence, The factory need 16 more employees to hire in order to keep the factory running as before.