Answer:
This project's optimal economic life is 3 years.
Explanation:
Note: See the attached excel file for the calculation of equivalent annual cost
In the attached excel file, the following is used:
Cost of Capital = 10% Â
From the attached excel file, the highest equivalent annual cost of $526 occurred in year 3. This implies that this project's optimal economic life is 3 years.