The master budget of Tenenbaum Ltd. shows that the planned activity level for next year is expected to be 30,000 machine hours. At this level of activity, the following manufacturing overhead costs are expected:

Indirect labor................................................. $720,000
Machine supplies..........................................180,000
Indirect materials..........................................210,000
Depreciation on factory building..................150,000
Total manufacturing overhead.....................$1,260,000

A flexible budget for a level of activity of 40,000 machine hours would show total manufacturing overhead costs of:________