Answer:
Order of processing the jobs:
Job Critical Ratio
C 1.375
D 1.667
A 1.75
B 2.0
E 2.2
Explanation:
a) Data and Calculations:
Job Processing Job due Critical
Time (days) date (days) Ratio
A 4 7 1.75 (7/4)
B 2 4 2.0 (4/2)
C 8 11 1.375 (11/8)
D 3 5 1.667 (5/3)
E 5 11 2.2 (11/5)
b) The critical ratio (CR) dispatching indicates the priority sequencing that should be adopted to process work at a work center. The first process is to create the CR priority index number, which is obtained from the formula of due days divided by the processing days. Therefore, the job with the lowest CR is scheduled first.