Answer:
A
Step-by-step explanation:
The data set is;
2,4,6,8,10,12
For a box plot, we need five information regarding a data set;
These are;
1. The minimum value
The minimum value here is 2, so the box plot starts from here
2. The lower quartile
This is the term according to the formula;
(n + 1)/4
Where n is the number of data points which is 6
So we have;
(6 + 1)/4 = 7/4 = 1.75
Approximately this is the second term which is 4
3. The median
This is the middle number
We only need to add the third and fourth term, then divide by 2
we have this as; (6 + 8)/2 = 14/2 = 7
4. The upper quartile
It is the term according to the formula;
3(n+ 1)/4 = 3 * 1.75 = 5th term approximately
So we have it as 10
5. The maximum value
The max value here is 12
So the points on the box plot are;
2,4,7,10 and 12
So the correct plot is the first one