Answer:
85 units
Explanation:
Annual demand = 3,400 units
Using 40 weeks per year & 4 days per week, the no of days per year = 160 days (40*4)
Average daily demand (d) = Annual demand / Number of days per year
Average daily demand (d) = 3400/160
Average daily demand (d) = 21.25 units
Lead time (L) = 4 days
Reorder point = Average daily demand (d) * Lead time (L)
Reorder point = 21.25 * 4
Reorder point = 85 units