Respuesta :
Answer:
Material price variance = 1250
Quantity variance = 300
Explanation:
Actual price of raw material = $1.75
Standard price = $1.50
Actual quantity = $5000
Material price variance = [Actual price - Standard price] x Actual quantity
Material price variance = [1.75 - 1.50] x 5000
Material price variance = 1250
Quantity variance = [Actual quantity - Standard quantity] x Standard price
Quantity variance = [5000 - 2400 x 2] x 1.50
Quantity variance = 300
Answer:
Material price variance $1,250
Material quantity variance $300
Explanation:
Calculation to determine the materials price and quantity variance
MATERIAL PRICE VARIANCE
Using this formula
Material price variance=(AP-SP)*AQ
Let plug in the formula
Material price variance=($1.75-$1.50)*5,000
Material price variance=$0.25*5,000
Material price variance=$1,250
Therefore Material price variance is $1,250
MATERIAL QUANTITY VARIANCE
Using this formula
Material quantity variance=(AQ-SQ)*SP
Let plug in the formula
Material quantity variance=(5,000-2*2,400)*$1.50
Material quantity variance=(5,000-4,800)*$1.50
Material quantity variance=200*$1.50
Material quantity variance=$300
Therefore Material quantity variance is $300