Answer:
Total cost of project  $123,025 Â
Explanation:
The total cost of the project would be the sum of the labour cost of the three consultants and the overhead charged to the project.
So, we can compute the total cost of project as follows:
Labour cost                           $
Senior consultant      (175× 120)  =      21,000
Other consultants     (130× 350)  =     45,500  Â
Total labour cost                       66,500
Overhead     (85%× 66,500)            56,525           Â
Total cost of project                   123,025           Â