The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $2,117. A total of 34 direct labor-hours and 224 machine-hours were worked on the job. The direct labor wage rate is $14 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $16 per machine-hour. The total cost for the job on its job cost sheet would be:_____.
a. $5,867.b. $10,637.c. $8,492.d. $5,448.

Respuesta :

Answer:

$6177

Explanation:

Calculation to determine what The total cost for the job on its job cost sheet would be

TOTAL COST

Direct materials $2,117

Direct labor (34 direct labor-hours × $14 per direct labor-hour) $476

Overhead (224 machine-hours × $16 per machine-hour) $3584

Total manufacturing cost

$6177