Answer:
Hence the demand for the product D = 25 units per min.
Explanation: Â
Units produced (C) = 150 Â
Time for production = 20 min Â
Time for transport = 5 min Â
Total time (T) = 20 + 5 = 25 min Â
Safety stock (S) = 20% Â
Number of Kanban (y) = 5 Â
Demand unit per min = D Â
[tex]y = D*T*(1+x)/C\\5 = D*25*(1+0.2)/150\\30 = D*1.2\\D = 30/12*10[/tex]
D= 25 units per min.