American Delights manufactures a wide variety of holiday and seasonal decorative items. American's activity-based costing overhead rates are:
Purchasing $380 per order
Storing $2 per square foot/days
Machining $100 per machine hour
Supervision $5 per direct labor hour
The Snow Man project involved three purchase orders, 4,000 square feet/days, 60 machine hours, and 40 direct labor hours. The cost of direct materials on the job was $19,000 and the direct labor rate is $30 per hour.
Determine the total cost of the Snow Man project.