Respuesta :
Grady, Inc.'s Direct Materials Budget, Direct Labor Budget, and Manufacturing Overhead Budget for the year are as follows:
Direct Materials Budget
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total
Projected production 650 500 450 600 2,200
Ounces of plastic per kit 4 4 4 4 4
Total materials required 2,600 2,000 1,800 2,400 8,800
Ending materials inventory 200 180 240 200
Raw materials available 2,800 2,180 2,040 2,600
Beginning materials inventory 850 200 180 240
Purchases of raw materials 1,950 1,980 1,860 2,360
Cost of materials purchased $1,950 $1,980 $1,860 $2,360 $8,150
Direct Labor Budget
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total
Projected production 650 500 450 600 2,200
Hours per kit 0.10 0.10 0.10 0.10 0.10
Total direct labor hours reqd. 65 50 45 60 220
Average cost per hour $10 $10 $10 $10 $10
Total direct labor cost $650 $500 $450 $600 $2,200
Manufacturing Overhead Budget:
Variable overhead $130 $100 $90 $120 $440
Fixed overhead $165 $165 $165 $165 $660
Total manufacturing o/h $295 $265 $255 $285 $1,100
Manufacturing overhead/unit $0.45 $0.53 $0.57 $0.475 $0.50
Cost per Kit:
Direct materials cost per unit = $4.00
Direct labor cost per unit $1.00
Manufacturing overhead $0.50
Cost per kit = $5.50
Cost of goods sold budget for the year:
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total
Quarter Sales 100 150 100 200 550
Cost per unit $5.50
Cost of goods sold $550 $825 $550 $1,100 $3,025
Learn more: https://brainly.com/question/13767214