The total cost of the Job in the question is; D: $87,500
We are given that;
Direct Labor = $25000
Cost of direct materials used = $50000
Overhead is 50% of direct labor costs. Thus;
Overhead Cost = 50% * $25000 = $12500
Total Cost of Job = Overhead Cost + Materials Cost + Labor Cost
Total Cost of Job = $87,500