In AON networks, "node" is a point where one or more lines (arrows) begin or terminate, commonly used for depicting an event or activity.
What is Activity-on-Node (AON) diagram?
Scheduling logic diagrams of the most fundamental kind. Any activity on the schedule that has no float; Total Float = 0; is considered a critical activity.
Between the project's start and finish, there are vital activity(s) that must be completed continuously. This is known as the critical path.
The importance of AON diagram are-
- Because it helps identify the essential path, the arrow diagram is crucial for the project timeline.
- The critical route is used to determine the most effective schedule while still achieving the objectives required for a project to be successful.
- The critical path indicates the longest time of every dependent task.
- It is possible to organize tasks and determine not only when they must be finished but also which ones must be performed and which ones can be skipped while still reaching the project's goals and objectives by creating a schedule. An arrow diagram is essential because of this.
- It results in the project's ideal schedule.