The budget for the department, assuming that it uses flexible budgeting is: $89,000.
First step is to calculate the direct labor cost
Direct Labor =2350 hours x( $72,000/2400)
Direct Labor=$70500
Second step is to calculate the Total Department Costs
Total Department Costs=$70,500+$18,500
Total Department Costs=$89,000
Therefore the budget for the department, assuming that it uses flexible budgeting is: $89,000.