29. The formula below is often used by project managers to compute, E, the estimated time to complete a job, where O is the shortest completion time, P is the longest completion time, and M is the most likely completion time. E = O + 4M + P 6​

Respuesta :

The formula below is often used by project managers to compute, E, the estimated time to complete a job, where O is the shortest completion time, P is the longest completion time, and M is the most likely completion time P = 6E - O - 4M.

Given, that E is the estimated time to complete a job.

O is the shortest completion time.

P is the longest completion time.

And, M is the most likely completion time.

The equation given, E = (O + 4M + P)/6

By balancing the equation, multiplying both sides by 6 we get

or, 6E = O + 4M + P

Now, subtracting O + 4M from both sides, we get

P = 6E - O - 4M.

Therefore, we get P in terms of P = 6E - O - 4M.