The team leader got this information from viewing the: Schedule Performance Index
Time table overall performance Index is used to expose or constitute the progression as compared to the venture schedule. here, in the given question, the team leader represents that $1.20 really worth of work is completed for every $1 worth of scheduled work. These records can most effectively be analyzed by SPI. different alternatives are wrong as we don't ought to forecast the earned value management.
Learn more about worth here - https://brainly.com/question/27218751