Respuesta :

It will take 1.5 hours for 16 men  to dig a trench 48 m long.

How can this be calculated?

It should be noted that the  time needed is direct proportional to the length of the trench, and inverse proportional to number of men.

The equation can be written as

t=kl/m..................................................... eqn(1)

Then if we substitute the given figures we have,

3=90k/15

Then k= 0.5

then substitute into eqn(1) we have

t=0.5 l/m

Therefore, since 16 men, 48m long,  is required, the time will now be calculated as :

t=0.5 48/16

t= 1.5 hrs.

Therefore, It will take 1.5 hours for 16 men  to dig a trench 48 m long.

Learn more about proportionality on:

https://brainly.com/question/21749206

#SPJ4