The expected completion time of a project is 40 weeks and the variance of its critical path activities is 9. what is the project completion time with a 75ertainty? select one:

Respuesta :

The expected completion time of a project is 40 weeks and the variance of its critical path activities is 9.Project completion time is 42.0325 weeks.

Variance of its critical path activity 9 weeks.

Therefore, Standard deviation of its critical path activity = Square root ( variance) = Square root (9) = 3

Project completion time with 5% certainty means probability of project completion - 0./5 Corresponding z value for probability of 0.75 = NORMSINV ( 0.75) = 0.6745

Therefore, project completion time with 75% certainty = Expected completion time of the project .

Value x Standard deviation of critical path activity = 40 weeks * 0.6745 x 3 weeks = 40-2.0235 = 42.0325 weeks

Learn more about Variance here

https://brainly.com/question/15858152

#SPJ4