Respuesta :

The slack for the activity that we have here is given to be 0

What is the slack of an activity?

This is the term that is used to solve for the difference that exists between the earliest start time and the latest finishing time.

The value of the slack is given as LS - ES

In the question, the value for LS = 8, while the value for ES IS EQUAL TO 8 hence we have

8 - 8 = 0

Therefore we conclude that the The slack for the activity that we have here is given to be 0

Read more on slack here: https://brainly.com/question/6197566