The term used to describe the likelihood(probability) that a project network's original critical path will change over the course of executing the project is Sensitivity.

How do you find the Critical path of a project?

1) List activities

2) Identify Dependencies

3) Create a network diagram

4) Estimate task duration

5) Calculate the critical path

6) Calculate the float

Through data-driven forecasting, project sensitivity is a comprehensive assessment of the likelihood that a project will be successful. Additionally, it distinguishes between high-risk and low-risk tasks, assesses risks' effects, and identifies dangers.

Hence, Project Sensitivity is the term used to describe the likelihood(Probability).

To learn more about the Critical path from the given link