Which of the following hypothetical critical path activities would be most beneficial to crash?
A.
Crash cost = low, normal time - crash time = high
B.
Crash cost = high, normal time - crash time = low
C.
Crash cost = low, normal time - crash time = low
D.
Crash cost = high, normal time - crash time = high