Respuesta :
Time taken to complete the project if two people worked together is required.
It would taken around 3.4 hours to complete the project if both the people worked together
Time taken to complete the work by first person is 6 hours
Time taken to complete the work by second person is 8 hours
The work equation will be be
[tex]\dfrac{1}{6}+\dfrac{1}{8}=\dfrac{1}{x}\\\Rightarrow \dfrac{4+3}{24}=\dfrac{1}{x}\\\Rightarrow x=\dfrac{24}{7}\approx 3.4\ \text{hours}[/tex]
So, it would taken around 3.4 hours to complete the project if both the people worked together.