Respuesta :
They would need to hire 20 more workers because they are 1/4 of the way done after the first two days. And that means they need to be 3/4 of the way done in the next 2 days, that means they have to be 3 times as productive from the first day and 10 times 3 equals 30, but they already have 10, so 30 - 10 = 20
THEY NEED 20 more workers
I hope it helps
THEY NEED 20 more workers
I hope it helps
Answer:
29 more workers are needed.
Step-by-step explanation:
Let us assume that the 10 workers, working at their normal rate would finish the job in exactly 8 days.
The rate of working for 1 worker is:
[ 1/10 of the job ] / [ 8 days ] = [ 1 job ] / [ 80 days ]
This is also [ 1/80 of the job ] / [ 1 day ]
In 2 days, the fraction of the job that gets done is:
[tex]2\times \frac{1}{80}=\frac{1}{40}[/tex]
Job left = [tex]1-\frac{1}{40} =\frac{39}{40}[/tex]
Now the rate has to be :
[tex]\frac{\frac{39}{40} }{2} =\frac{39}{80}[/tex]
Now, let w be the additional number of workers needed.
We get:
[tex]\frac{10+w}{80}=\frac{39}{80}[/tex]
Solving for w;
[tex]10+w=39[/tex]
[tex]w=39-10[/tex]
w = 29
Therefore, 29 more workers are needed.
-------------------------------------------------------------------------------------
There can be another approach as well.
Fraction of the job done by 10 workers in 2 days = 1/4
Remaining fraction = 1-1/4 = 3/4
Lets say W workers are needed more.
So, we can say that 3/4 of the work is to be done by 10+W workers.
Hence, it will take a total of 30 workers to complete the job.
Making it additional 20 workers.