Respuesta :
Answer:
9.3125 hours
Step-by-step explanation:
Given:
Number of components consisting in a product = 25
Standard time for work cycle = 7.45 minutes
or
standard time for work cycle = [tex]\frac{\textup{7.45}}{\textup{60}}[/tex] hours
Number of units completed = 75
Now,
The number of standard hours
= Number of units completed × standard time for the work cycle
= [tex]75\times\frac{\textup{7.45}}{\textup{60}}[/tex] hours
or
The number of standard hours = 9.3125 hours