Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days. Select one: a. day 7 b. day 5 c. Cannot be calculated based upon information given. d. day 3