A group of students are working on a project. They complete 30%percent of the project in 12 hours. If they continue to work at the same speed, how many hours will it take the group to finish the project

Respuesta :

mumsy

Answer: 40 HOURS

Step-by-step explanation:

If the students complete 30% of the project in 12 hours,

that means:

12 h................................30%

? h...................................100%

(12*100)/30= 40H

THE STUDENTS NEED 40H TO COMPLETE THE PROJECT

It will take 40 hours for the group to finish the project.

How many hours will it take the group to finish the project?

If the students complete 30% of the project in 12 hours,

that means:

⇒ 12 h = 30%

⇒ ? h = 100%

By using percentage theory:

Percentage formula = (Value/Total value) × 100.

⇒ (12*100)/30= 40H

The answer is 40 hours.

What are a percentage and its formula?

To determine the percentage, we have to divide the value by the total value and then multiply the resultant by 100. Percentage formula = (Value/Total value) × 100.

Learn more about percentage here: brainly.com/question/843074

#SPJ2